Tese de Doutorado
DOI
https://doi.org/10.11606/T.3.2017.tde-23032017-150255
Documento
Autor
Nome completo
Rosemary Boettger Giardinetto
E-mail
Unidade da USP
Área do Conhecimento
Data de Defesa
Imprenta
São Paulo, 2014
Orientador
Banca examinadora
Martini, Jose Sidnei Colombo (Presidente)
Burani, Geraldo Francisco
Jardini, José Antonio
Magrini, Luiz Carlos
Sousa, Thales
Título em português
Repotencialização de linhas de transmissão localizadas em áreas de severas restrições ambientais.
Palavras-chave em português
Cabos elétricos
Linhas aéreas de transmissão de energia elétrica
Monitoramento
Resumo em português
Os cerca de 107.000 km de linhas de transmissão existentes no Brasil, nas tensões de 138/230/345/440/500/750 kV (corrente alternada), e 600 kV (corrente continua), atravessam parques nacionais ou estaduais, estradas, rios e parte se encontra com sobrecarga. O aumento da capacidade de carregamento das linhas de transmissão, se feito da forma tradicional, com a substituição ou reforço nas estruturas e fundações, em faixas que cruzam áreas consideradas de preservação ambiental permanente, exige obras adicionais que alteram o meio ambiente e desta forma, com os rigores da atual legislação ambiental, torna inviável tais alterações ou substituição. Uma das formas encontradas é a utilização de novas tecnologias em cabos condutores aéreos. Este trabalho tem a finalidade de pesquisar as necessidades do recondutoramento da linha de transmissão, com a minimização/eliminação dos danos ao meio ambiente. Uma das alternativas encontradas é a utilização de cabos especiais, que por se tratar de nova tecnologia em cabos, e considerando o desconhecimento de seu desempenho efetivo em condições reais, surge a necessidade da verificação de seu comportamento. Este trabalho apresenta a análise de casos no Brasil e o desenvolvimento piloto de um sistema de monitoramento em tempo real, através de medições diretas e indiretas, no trecho de linha de transmissão onde foi instalado um condutor de nova tecnologia, a fim de acompanhar o desempenho das características elétricas e mecânicas do novo condutor. Como resultado final foram validados os valores de projeto da ampliação da capacidade da linha de transmissão, sem impactos ao meio ambiente.
Título em inglês
Uprating of transmission lines in areas of severe environmental constrains.
Palavras-chave em inglês
Electric cables
Monitoring
Overthead transmission lines of electric energy
Resumo em inglês
The approximately 107,000 km of transmission lines existing in Brazil, operating at 138 kV, 230 kV, 345 kV, 440 kV, 500 kV, 750 kV(ac) and 600 kV(dc), regularly encounter and cross state or national parks as well as highways, rivers and parks. Due to the ever increasing demand of power most of these transmission lines are at present overloaded. Increasing the loading capacity of these transmission lines in the traditional way (i.e. by substituting or reinforcing the structures and foundations in areas of permanent preservation) require additional works that may alter the environment; thus, making unfeasible the application of such alterations in view of the current strict environmental regulations. One way to cope with such a problem is through the utilization of new technologies applied to cables. Therefore, the objective of this work is to investigate the alternative of reconductoring a transmission line causing a minimum damage (and if possible eliminating this damage) to the environment. One of the alternatives found is the use of special cables which due to its relatively new introduction and technology to the power industry demands a thorough study on issues like the performance and verification of its behavior under real conditions. This work presents the development of a real-time monitoring system through direct and indirect measurements performed on a transmission line segment where a special conductor was installed. During the course of the research the performance of the new conductor regarding its electrical and mechanical characteristics was monitored. The measurements performed showed to be coherent with those obtained during the design of the transmission line.
 
AVISO - A consulta a este documento fica condicionada na aceitação das seguintes condições de uso:
Este trabalho é somente para uso privado de atividades de pesquisa e ensino. Não é autorizada sua reprodução para quaisquer fins lucrativos. Esta reserva de direitos abrange a todos os dados do documento bem como seu conteúdo. Na utilização ou citação de partes do documento é obrigatório mencionar nome da pessoa autora do trabalho.
Data de Publicação
2017-03-23
 
AVISO: Saiba o que são os trabalhos decorrentes clicando aqui.
Todos os direitos da tese/dissertação são de seus autores
CeTI-SC/STI
Biblioteca Digital de Teses e Dissertações da USP. Copyright © 2001-2024. Todos os direitos reservados.