Tesis Doctoral
DOI
https://doi.org/10.11606/T.18.1999.tde-11062024-110818
Documento
Autor
Nombre completo
Helenilza Ferreira Albuquerque Cunha
Instituto/Escuela/Facultad
Área de Conocimiento
Fecha de Defensa
Publicación
São Carlos, 1999
Director
Tribunal
Calijuri, Maria do Carmo (Presidente)
Chaudhry, Fazal Hussain
Nordi, Nivaldo
Salati, Eneida
Vazoller, Rosana Filomena
Título en portugués
Avaliação da eficácia de medida mitigatória de impactos sócio-ambientais causados por construção de hidrelétricas : o reassentamento populacional de UHE de Taquaruçu-SP
Palabras clave en portugués
condições de vida
impactos sócio-ambientais
medidas mitigadoras
reassentamento populacional involuntário
usinas hidrelétricas
Resumen en portugués
A Companhia Energética de São Paulo (CESP) construiu no período de 1980 e 1992 a barragem de Taquaruçu para geração de energia elétrica. A barragem foi edificada no Rio Paranapanema, entre os municípios de Sandovalina (SP) e Itaguagé (PR),formando um lago de 105,5 km por metro quadrado. Houve a necessidade de um programa de reassentamento de pequenos produtores rurais que habitavam as regiões ribeirinhas que seriam alagadas. No escopo do EIA/RIMA da obra a ser executada foramprevistas medidas mitigadoras dos impactos sócio-ambientais. Esta pesquisa apresenta uma avaliação da eficácia dessas medidas na minimização dos impactos sócio-ambientais causados pela construção da Usina Hidrelétrica (UHE) de Taquaruçu.Primeiramente foi realizada uma avaliação em campo das condições de vida da população reassentada em 1992, estabelecendo um paralelo entre a situação sócio-ambiental anterior e posterior ao reassentamento Fazenda Laranjeiras no Município deNarandiba (SP), no intuito de identificar os impactos causados pela obra. Os dados obtidos pela investigação de campo receberam tratamento estatísco. Paralelamente foi feita uma análise descritiva de projetos anteriores de reassentamentos daCESP tais como Lagoa São Paulo (1978) e Rosanela (1986). Os resultados obtidos pelas análises, estatistica e descritiva, indicaram a diminuição da satisfação da população, principalmente com a infra-estrutura do reassentamento. No reassentamentode Laranjeiras as carências mais observadas foram no sistema de transporte e nos serviços de saúde. Há ncessidade de se trabalhar com maior ênfase as variáveis sociais específicas desses projetos, que geralmente não são consideradas, a fim de melhor atender aos interesses e particularidades das populações reassentadas
Título en inglés
Evaluation of socioenvironmental mitigation measures caused by the construction of hydropower plants : the populational resettlement of the Taquaruçu power plant, São Paulo, Brazil
Palabras clave en inglés
hydropower
negative effects mitigatíon
population living conditions
populational involuntary resettlement
socio-environmental impact
Resumen en inglés
The Electricity Company of São Paulo (CESP), Brazil, constructed from 1980 to 1992 the Taquamçu Dam for the generation of hydropower. Forming a reservoir of 105,5 km , the dam was built on the Paranapanema River between the municipalities of Sandovalina (SP) and Itaguagé (PR). A program for the resettlement of a small group of rural producers which lived on the flooded área was necessary. hi the Environmental Impact Study and in the Environmental Impacts Report of the dam, mitigation measures on the socioenvironmental ímpacts were proposed. This research presents an evaluation ofthe efficiency ofthese measures on minimizing the socioenvironmental impacts caused by the construction of the Taquaruçu Power Plant. FÍrstly an evaluation of the population living conditions was conducted establishing a comparison between the population s socioenvironmental situation before and after the resettlement 'Tazenda Laranjeiras" (1992), in the municipality of Narandiba (SP). The obtained data during the field investigation received statístical treatment. Simultaneously, previous CESP resettlement projects as Lagoa São Paulo (1978) and Rosanela (1986) were described. The results of the statistícal and descriptive analysis indicated a diminishment of population7s satisfaction, specially with the infrastructure in the resettlement area. In the Laranjeiras Resettlement the main needs observed were in the transportation system and in the health service. It is necessary to emphasize specific social variables in this kind of projects, which are generaly not considered, to better attend the interests and particular needs of resettled populations
 
ADVERTENCIA - La consulta de este documento queda condicionada a la aceptación de las siguientes condiciones de uso:
Este documento es únicamente para usos privados enmarcados en actividades de investigación y docencia. No se autoriza su reproducción con finalidades de lucro. Esta reserva de derechos afecta tanto los datos del documento como a sus contenidos. En la utilización o cita de partes del documento es obligado indicar el nombre de la persona autora.
Fecha de Publicación
2024-06-11
 
ADVERTENCIA: Aprenda que son los trabajos derivados haciendo clic aquí.
Todos los derechos de la tesis/disertación pertenecen a los autores
CeTI-SC/STI
Biblioteca Digital de Tesis y Disertaciones de la USP. Copyright © 2001-2024. Todos los derechos reservados.