Tese de Doutorado
DOI
https://doi.org/10.11606/T.18.1999.tde-11062024-110818
Documento
Autor
Nome completo
Helenilza Ferreira Albuquerque Cunha
Unidade da USP
Área do Conhecimento
Data de Defesa
Imprenta
São Carlos, 1999
Orientador
Banca examinadora
Calijuri, Maria do Carmo (Presidente)
Chaudhry, Fazal Hussain
Nordi, Nivaldo
Salati, Eneida
Vazoller, Rosana Filomena
Título em português
Avaliação da eficácia de medida mitigatória de impactos sócio-ambientais causados por construção de hidrelétricas : o reassentamento populacional de UHE de Taquaruçu-SP
Palavras-chave em português
condições de vida
impactos sócio-ambientais
medidas mitigadoras
reassentamento populacional involuntário
usinas hidrelétricas
Resumo em português
A Companhia Energética de São Paulo (CESP) construiu no período de 1980 e 1992 a barragem de Taquaruçu para geração de energia elétrica. A barragem foi edificada no Rio Paranapanema, entre os municípios de Sandovalina (SP) e Itaguagé (PR),formando um lago de 105,5 km por metro quadrado. Houve a necessidade de um programa de reassentamento de pequenos produtores rurais que habitavam as regiões ribeirinhas que seriam alagadas. No escopo do EIA/RIMA da obra a ser executada foramprevistas medidas mitigadoras dos impactos sócio-ambientais. Esta pesquisa apresenta uma avaliação da eficácia dessas medidas na minimização dos impactos sócio-ambientais causados pela construção da Usina Hidrelétrica (UHE) de Taquaruçu.Primeiramente foi realizada uma avaliação em campo das condições de vida da população reassentada em 1992, estabelecendo um paralelo entre a situação sócio-ambiental anterior e posterior ao reassentamento Fazenda Laranjeiras no Município deNarandiba (SP), no intuito de identificar os impactos causados pela obra. Os dados obtidos pela investigação de campo receberam tratamento estatísco. Paralelamente foi feita uma análise descritiva de projetos anteriores de reassentamentos daCESP tais como Lagoa São Paulo (1978) e Rosanela (1986). Os resultados obtidos pelas análises, estatistica e descritiva, indicaram a diminuição da satisfação da população, principalmente com a infra-estrutura do reassentamento. No reassentamentode Laranjeiras as carências mais observadas foram no sistema de transporte e nos serviços de saúde. Há ncessidade de se trabalhar com maior ênfase as variáveis sociais específicas desses projetos, que geralmente não são consideradas, a fim de melhor atender aos interesses e particularidades das populações reassentadas
Título em inglês
Evaluation of socioenvironmental mitigation measures caused by the construction of hydropower plants : the populational resettlement of the Taquaruçu power plant, São Paulo, Brazil
Palavras-chave em inglês
hydropower
negative effects mitigatíon
population living conditions
populational involuntary resettlement
socio-environmental impact
Resumo em inglês
The Electricity Company of São Paulo (CESP), Brazil, constructed from 1980 to 1992 the Taquamçu Dam for the generation of hydropower. Forming a reservoir of 105,5 km , the dam was built on the Paranapanema River between the municipalities of Sandovalina (SP) and Itaguagé (PR). A program for the resettlement of a small group of rural producers which lived on the flooded área was necessary. hi the Environmental Impact Study and in the Environmental Impacts Report of the dam, mitigation measures on the socioenvironmental ímpacts were proposed. This research presents an evaluation ofthe efficiency ofthese measures on minimizing the socioenvironmental impacts caused by the construction of the Taquaruçu Power Plant. FÍrstly an evaluation of the population living conditions was conducted establishing a comparison between the population s socioenvironmental situation before and after the resettlement 'Tazenda Laranjeiras" (1992), in the municipality of Narandiba (SP). The obtained data during the field investigation received statístical treatment. Simultaneously, previous CESP resettlement projects as Lagoa São Paulo (1978) and Rosanela (1986) were described. The results of the statistícal and descriptive analysis indicated a diminishment of population7s satisfaction, specially with the infrastructure in the resettlement area. In the Laranjeiras Resettlement the main needs observed were in the transportation system and in the health service. It is necessary to emphasize specific social variables in this kind of projects, which are generaly not considered, to better attend the interests and particular needs of resettled populations
 
AVISO - A consulta a este documento fica condicionada na aceitação das seguintes condições de uso:
Este trabalho é somente para uso privado de atividades de pesquisa e ensino. Não é autorizada sua reprodução para quaisquer fins lucrativos. Esta reserva de direitos abrange a todos os dados do documento bem como seu conteúdo. Na utilização ou citação de partes do documento é obrigatório mencionar nome da pessoa autora do trabalho.
Data de Publicação
2024-06-11
 
AVISO: Saiba o que são os trabalhos decorrentes clicando aqui.
Todos os direitos da tese/dissertação são de seus autores
CeTI-SC/STI
Biblioteca Digital de Teses e Dissertações da USP. Copyright © 2001-2024. Todos os direitos reservados.